OEM and ODM toy development: the path from brief to production

Most toy projects fail between the sample and the shipment, not in the design. The gap is documentation: what was approved, in which version, with which components.

Most toy projects fail between the sample and the shipment, not in the design. The gap i
Most toy projects fail between the sample and the shipment, not in the design. The gap is documentation: what was approved, in which version, with which components.

OEM, ODM and the difference that matters

In OEM, the buyer owns the design and the factory builds it. In ODM, the factory owns a design and the buyer puts a brand on it, sometimes with small changes.

The distinction is commercial rather than technical, and it decides who is responsible when a component changes. An ODM buyer who asks for a material change has started an OEM conversation without knowing it.

The contract should state which model applies and who owns the tooling. Tooling ownership is the clause that decides whether a buyer can move the product to another factory.

A buyer who does not own the tooling has a supplier for the life of the product, whatever the contract says about competition.

The brief that prevents a thousand samples

A brief that specifies the product's function, its age grading, its target market, its price point and its packaging format gives a factory enough to propose a design.

A brief that specifies a feeling - 'like a well-known brand but cheaper' - gives a factory a licence to interpret, and the interpretation will be wrong in at least one dimension.

The most useful attachment is a physical reference: a competitor's product, a previous version, or a handmade model. A reference object carries more information than a page of adjectives.

The brief should also state what is fixed and what is open. A buyer who says 'the shell must be silicone' and 'the price must be under two dollars' has defined a real problem; one who says 'make it premium' has not.

Sample stages and the sign-off discipline

Development usually runs through three samples: a concept sample, a pre-production sample and a production sample. Each has a different purpose and a different sign-off.

The concept sample proves the idea. It is often handmade and it should not be used to set tolerances, because its dimensions are not the tool's dimensions.

The pre-production sample proves the tool and the process. It is the sample that should be measured, tested and approved, and it is the one that most projects rush.

The production sample proves the line. It should be drawn from the first production run and held against the approved pre-production sample, with the differences recorded.

Documentation: the four documents that settle arguments

The approved sample with its date and revision, the specification sheet with its tolerances, the test reports for the destination market, and the packaging artwork with its version.

These four are the reference set. When a shipment is questioned, the answer is a comparison against them, not a memory of a conversation.

The specification sheet should carry the numbers that matter: dimensions with tolerances, weight, material, colour standard, hardness or fill, and the packaging's dimensions.

A specification that says 'as sample' is a specification that transfers responsibility to a physical object that will be lost. The object should be the reference and the sheet should carry the numbers.

Changes, and the cost of a silent one

Factories change things. A material is substituted, a colour is matched to a different standard, a component's supplier changes, and nobody tells the buyer because the sample still looks right.

The defence is a change notification clause: any change to material, component, process or sub-supplier is notified in writing before it is implemented, with a new sample for approval.

The clause is only effective if the buyer audits against it. A first-article inspection on each shipment, against the specification sheet, is the audit.

A silent change discovered at retail is expensive: a recall, a chargeback, or a brand's reputation. The clause costs nothing and the inspection costs a day.

The first production run and the inspection plan

The first run should be inspected at three points: incoming material, in-process at the critical operations, and final random inspection before packing.

The critical operations are the ones that create the product's function: the moulding, the fill, the seal, the print. Inspection at those points catches the failures that final inspection cannot see.

The final inspection should use a defined sampling plan and a defined list of defects, with critical, major and minor classifications. 'Looks fine' is not an inspection.

The plan should be agreed before the purchase order, not after the first shipment. A plan agreed afterwards is a plan negotiated with a shipment already on the water.

Costing a programme before the sample

The cost of a toy is fixed by four things: the tool, the material, the cycle time and the packing labour. A buyer who quotes a target price without those four is quoting a wish.

The tool is a one-off and it is amortised over the order. A small order with a complex tool carries a tool cost per unit that the buyer often forgets when comparing quotes.

Cycle time is set by wall thickness and by the cooling in the tool. A part that is two millimetres thicker takes disproportionately longer, and the difference shows up in the unit price.

Packing labour is the item that varies most between factories. A kit that is assembled by hand in a small factory and one that is assembled on a line can differ by a third in cost.

The audit and the file

A factory audit covers four areas: the quality system, the production controls, the social compliance and the product's technical file. Most buyers do the first and skip the last.

The technical file is where the product's compliance lives, and it is the document a retail buyer will ask for. A factory that cannot produce it is a factory that will fail the retail audit.

The file should be reviewed at the pre-production stage, when it can still be changed, rather than at shipment when it cannot.

A buyer who audits the file once and keeps it current spends less time on compliance than one who rebuilds it for every order.

The tool that is amortised over three years

Tool cost per unit depends on the order volume and on the tool's life. A tool built for a hundred thousand shots is cheaper than one built for a million.

The buyer should know the tool's expected life and the volume it assumes. A tool that wears out in year two is a cost that was not in the quote.

The colour proof that arrives after the packaging

Packaging is printed before the product is approved in most programmes, and the colour on the box is then a promise the product has to meet.

The proof should be made from the approved sample, and the box should be printed after the sample is signed. The sequence costs a week and prevents a season of mismatched product.

The component that is sourced twice

A kit's components are often sourced from several suppliers, and a change in one supplier's component can make the kit non-compliant without anyone noticing.

The bill of materials should name the supplier for each component and the change notification should cover sub-suppliers, not just the factory.

The factory that is audited once

A factory audit is a snapshot. The conditions that produced the snapshot can change within a quarter, especially in a busy season.

The audit should be repeated annually and supplemented by the first-article inspection on each shipment. The inspection is the ongoing evidence.

The document that decides a recall

A recall is decided by traceability: which batch, which components, which date. A factory that cannot trace a batch cannot limit a recall.

The batch record should link the raw material lots to the production date and the carton range. It is the cheapest insurance in the programme.

The price that moves after the sample

A quoted price is based on assumptions: volume, packing method, material grade. A change in any of them moves the price, and the movement is usually discovered at the purchase order.

The quote should state its assumptions, and the purchase order should confirm them. Two documents that prevent the conversation nobody wants in the fourth quarter.

For a programme that starts from a buyer's brief rather than a catalogue, the OEM/ODM play dough programme is the example of an ODM product that can carry a private label.

What to check

  • OEM or ODM stated in the contract, with tooling ownership
  • Brief includes function, age grading, market, price and packaging
  • Physical reference supplied alongside the written brief
  • Pre-production sample measured, tested and signed with a date
  • Four-document reference set held by both parties
  • Written change notification clause with first-article inspection